In December 2018 PrJSC Electrometallurgical works Dneprospetsstal named after A.N.Kuzmin» produced 18 165 tons of steel that is the is by 3,1% less than in November 2018. 11 888 tons of rolled stock produced for the same period that is by 3,5%less than in November 2018.
The total cost of the commodity output was 768 510 thousand UAH (in established prices) in December 2018. It is 0,7% more than the last month figures.
For 12 months in 2018 delivered 247 028 tons of steel (by 4,5% less than in the same period of last year) and produced 162 638 tons of rolled products (by 3,9% less than in the same period of last year).
During 12 months of 2018 the production of commercial products was 9 635 547 thousand UAH. It is 17,7% more than the same period of 2017.
Taking into account the tendency of the resources cost growth according to the results of work for the period of January-December 2018, the plant’s profitability index is negative.
|